Bau-Lundu dual carriageway achieves 90% land acquisition, utility relocation underway

Facebook
X
WhatsApp
Telegram
Email
Henry (centre) with the Village Security and Development Committee (JKKK) of Pekan Bau posing for a photo with LED lights in the background along Jalan Datuk Temenggong Salau.

LET’S READ SUARA SARAWAK/ NEW SARAWAK TRIBUNE E-PAPER FOR FREE AS ​​EARLY AS 2 AM EVERY DAY. CLICK LINK

BAU: The first Bau-Lundu dual carriageway upgrading project has completed a 90 per cent land acquisition.

Deputy Transport Minister (River and Sea), Datuk Henry Harry Jinep said that the project went smoothly, with the government paying land compensation to affected owners and relocating utilities along the project site.

The primary issue is the relocation of utilities. We have large pipes, water pipes, and power supplies along the road. These cannot interfere with our community.

“If they are relocated, it should not affect the people’s daily life in Bau,” he said to the media after launching the Bau Gateway last night.

Earlier, Deputy Infrastructure Minister Datuk Aidel Lariwoo stated that the project involves the upgrading of the existing single carriageway (R5 standard of the Public Works Department – JKR) to a dual carriageway (U5 standard) for 3.65km at a contract sum of RM74 million.

He also mentioned that the dual carriageway is almost equivalent to the Pan Borneo Highway and leads directly from the Pan Borneo Highway to Bau Town.

See also  Flood woes to be over soon

“The construction works are a little slower because there are utility issues like water supply, electricity poles, telecommunication lines, and many residential houses involved with the road construction,” he said.

However, he believes the JKR is doing its best to liaise with the Land and Survey Department and the relevant utility authorities to resolve these issues.

Meanwhile, Henry, also the Tasik Biru assemblyman, said the Rural Transformation Project (RTP) in his constituency is also going smoothly.

“We adhere to the process whereby the Land and Survey Department determines the land and ensures there are no hindrances.

“If we proceed with the identification of sites, they can begin implementation. There will be some delay, but I don’t see any critical issues,” he said.

Related News

Most Viewed Last 2 Days

Los Angeles Recovers From Historically Devastating Wildfires
Number of deaths in California wildfires rises to 29
local paddy field, food supply
Thailand's rice exports hit 6-year high in 2024
President Trump Returns To The White House From Florida
US federal judge blocks Trump admin's freeze on federal financial assistance
43764476ced1da8619b7dd12390dccf36798d42dcce3d
King, Queen extend Chinese New Year greetings
flood evacuation centre
Non-stop rain worsens floods, forces 1,097 into relief centres